Description of WEC IW(P)Ps
|
Project |
Water
(m3/ day) |
Power (MW) |
Fuel Type |
Status |
Project Cost (Million USD) |
Initial Commercial Operations Date (ICOD) |
Project Commercial Operations Date (PCOD) |
|
Shuaibah
(Phase 3)
IWPP |
880,000 |
900 |
Arabian Light Crude Oil |
Projet completion is 88.9 % as on 31-Mar-2008. |
2,460 |
05 - Feb- 2009 |
25-Jul - 2009 |
|
Shuqaiq
(Phase 2)
IWPP |
212,000 |
850 |
Arabian Heavy Crude Oil |
Project completion is 25.9 % as on 31-Mar-2008. |
1,870 |
01-May-2010 |
01-Dec-2010 |
|
Shuaibah Expansion
IWP |
150,000 |
- |
- |
Project completion is 71.72 % as on 31-Mar-2008. |
234 |
- |
28-Feb-2009 |
|
Ras Az Zawr
IWPP |
1,000,000 |
850 – 1100 |
Arabian Heavy Crude Oil |
RFP issued on 15-June-2007.
Bid submission date is
28-Jun-2008 |
>5,300 |
15-Mar-2012 |
30-Aug-2012 |
|
|
|
|
|
|
|
|